Project Description

Project Details

Project Owner:

Confidential

Contractor:

Austin Commercial

Structural Engineer:

SSOE Group

Architect:

Confidential

Steel Tonnage:

42,000 tons

Location:

Austin, Texas

Schuff Services:

project management
steel erection

Project Overview

The greatest complexities of this project included the fast paced schedule, extensive square footage/steel tonnage and workforce demand in an extraordinarily strained labor market. Due to the size of the job, two general contractors were selected and the scope was split between them. Our team completed the scope of erecting 38k tons in 4.5 months.

In order to staff this job, it was essential for us to have the ability to supply many of our own skilled workforce to supplement the enormous demand required to meet such an aggressive schedule.